Chronological Review of Construction Details
|
1999 | 2000 | 2001 | 2002 | ||||||||||||||
1 | Preparatory work (26 weeks) | ||||||||||||||||
2 | Utility construction (26 weeks) | ||||||||||||||||
3 | Civil engineering work on the Kelenföld train station - Szt. Gellért tér section (104 weeks) | ||||||||||||||||
4 | Civil engineering work on the Szt. Gellért tér - Keleti train station section (91 weeks) | ||||||||||||||||
5 | Track construction (91 weeks) | ||||||||||||||||
6 | Construction in connection with electricity supply (building substations) (91 weeks) | ||||||||||||||||
7 | Installing tunnel equipment (78 weeks) | ||||||||||||||||
8 | Substation construction (156 weeks) | ||||||||||||||||
9 | Constructing vehicle depot and maintenance shop (104 weeks) | ||||||||||||||||
10 | Purchasing trains (156 weeks) | ||||||||||||||||
11 | Building the Kelenföld train station junction (surface construction) (104 weeks) | ||||||||||||||||
12 | Building the Keleti train station junction (surface construction) (104 weeks) | ||||||||||||||||
13 | Test run (13 weeks) | ||||||||||||||||
14 | Installation | * |
|