4. metróvonal


Chronological Review of Construction Details


1999 2000 2001 2002
1 Preparatory work (26 weeks)  
2 Utility construction (26 weeks)  
3 Civil engineering work on the Kelenföld train station - Szt. Gellért tér section (104 weeks)  
4 Civil engineering work on the Szt. Gellért tér - Keleti train station section (91 weeks)  
5 Track construction (91 weeks)  
6 Construction in connection with electricity supply (building substations) (91 weeks)  
7 Installing tunnel equipment (78 weeks)  
8 Substation construction (156 weeks)  
9 Constructing vehicle depot and maintenance shop (104 weeks)  
10 Purchasing trains (156 weeks)  
11 Building the Kelenföld train station junction (surface construction) (104 weeks)  
12 Building the Keleti train station junction (surface construction) (104 weeks)  
13 Test run (13 weeks)  
14 Installation *