Previous Next


BUDAPEST METRO LINE 4 FEASIBILITY STUDY

Oktober 1996

TRANSPORT PLANNING Assessment

Introduction

Chapter 5 and Table 5.1 summarised the long list of alternatives being considered. Clearly detailed evaluation could not be undertaken for each possible alternative and we therefore undertook a long list review which aimed to sift the elements of each option and to define a short list testing programme.

The purpose of the long list review is to examine each option according to defined criteria, to conclude as to their worth and to prepare a testing programme for a short list detailed assessment. The key transport criteria for sifting through the various alternatives are outlined below:

  1. Change in flows on bridges across the Danube
  2. Relief to other services - bus and tram
  3. Journey time savings
  4. Economic costs and benefits
  5. Other key factors such as environmental, catchment area served, etc

With respect to journey time savings at the long list review level, we have run the forecast model for the base year only. Growth in travel, changes in economic parameters such as the value of time and increasing road congestion have not been taken into account at this stage.

An economic analysis has been undertaken on the basis of the base year travel estimates and economic parameters. The estimated benefits will therefore be significantly understated. However, we consider that the results can be used for comparison purposes between options. The costs and benefits were annualised based on a 10% discount rate, a 50 year life and zero residual value for the capital.

The long list assessment should then be one of judging which alternatives contribute most to improving transport and which best complement the existing public transport services. The aim is to define a realistic surface mode and LRT alternative for comparison and evaluation against the Metro alternatives. Hence we have structured the assessment within the principal mode options and assessed alternatives or sub-alternatives within these.

The alternatives and sub alternatives were tested using the base year transport forecast model described in Chapter 3. For each of the group of tests a number of assumptions were made regarding the rationalisation of existing public transport services. This was in order to understand the relationship between existing and the future services offered by the new facility. As the rationalisation did not remain constant between the groups of alternatives the results of the tests cannot be compared between the groups, i.e. comparisons can only be made between alternatives which are within the same group.

The analysis needed to address a number of issues:

  1. What is the preferred termination point on the Pest side
  2. What is the preferred alignment on the Buda side
  3. For LRT how should it cross the Danube- on the surface or underground and in what location - the choice being either at Erzsébet bridge or Szabadság bridge
  4. For Metro is the extension of Metro Line 2 from Déli station worthy of further investigation.

Do Minimum Option

The options are analysed against a Do Minimum option which is described in greater detail in Chapter 9. It includes the rehabilitation of Szabadság bridge at a cost of 19 Million ECU for the purposes of the economic assessments. Without this rehabilitation, Szabadság bridge could not continue to provide a route for the existing trams and diverting all passengers who currently use the tram services on Szabadság bridge to other adjacent crossings is not considered a realistic long term solution.

Surface Option

The surface alternatives included:

  • Bus based alternative - Alternative 1.1
  • Tram based alternative - Alternative 1.2

Based on the above key transport criteria, our conclusion was that an alternative should be developed, which is a combination of the alternatives tested, consisting of the following:

  1. increased provision of the tram services 4 and 6 and extension of Tram Line 4 to Kelenföld;
  2. increased provision of the Family of 7 buses in the context of satisfactory traffic arrangements but not to the level in this long list test;
  3. increased provision of tram routes 47 and 49 trams to a realistic level which is compatible with the increase in the provision of buses.

LRT Option

The 6 alternatives developed in Chapter 5 were first considered. The variants occurred as there were 2 sub-choices; firstly to either go underground or on the surface at Szabadság bridge and secondly to cross over the Danube at Erzsébet or Szabadság bridge. For Szabadság bridge, it was considered that the underground LRT alternative will return passenger benefits which are comparable to that of an underground metro alternative. The construction costs for an underground system based on a 'Light urban metro' or 'LRT' were expected to be virtually identical once the construction methods have been optimised for an underground system which will be the subject of Stage 2 of this study. At this stage of the study it was therefore not considered necessary to assess the underground LRT alternative at Szabadság bridge.

Four LRT alternatives which are fully segregated and partly running at street level were therefore reviewed. They are described as follows:

  1. LRT over Erzsébet bridge, via Bartók Béla út to Keleti - Alternative 2.1.1
  2. LRT over Erzsébet bridge, via Fehérvári út to Keleti - Alternative 2.1.2.
  3. LRT over Szabadság bridge, via Bartók Béla út to Astoria - Alternative 2.2.1.a
  4. LRT over Szabadság bridge, via Fehérvári út to Astoria - Alternative 2.2.2.a

Based on the key transport criteria defined above, our conclusion was as follows:

The preference was for the LRT alternative to cross at Szabadság bridge because of the differences in costs, the effects upon heritage with the Erzsébet alternatives and the greater benefits of the Szabadság alternatives. With regard to alignments, the Fehérvári alternative has some 11% higher benefits but at 13% more cost. The differences are very close and we had therefore included both of the Szabadság alternative alignments in the short list.

Metro Option

There were 3 sub-alternatives within the metro family at this long list review stage.

  1. Pest alignments
  2. Buda alignments
  3. Extension to Line 2 from Déli station to Kelenföld

  • Pest Alignments

To review the Pest sub-alternatives developed in Chapter 5 on a consistent basis, the Buda alignment was kept constant on the Tétényi út alignment (3.#.3). Reorganisation of existing services was kept identical for all of these alternatives.

Based on the key transport criteria defined in the above paragraph our conclusion was that the Keleti via Rákóczi alternative is preferred (3.3.3). It has 50% better benefits than the Astoria alternative, provides access to a new catchment area around Rákóczi and to Keleti station, whereas the Blaha alternative serves an area which is already served by Metro line 2. The cost of the Rákóczi alternative is some 4% higher than that of the Blaha alternative and the difference in economic benefits is some 18% in favour of the Rákóczi alternative. In terms of overall economic benefits the two alternatives are similar with the advantage being in the favour of the Rákóczi alternative.

  • Buda Alignments

The Buda alternatives were based on the same Pest alignment with a termination at Astoria to ensure compatible comparisons for these alternatives. The alternatives were:

  1. Metro via Bartók Béla út to Astoria - alternative 3.1.1
  2. Metro via Fehérvári út to Astoria - alternative 3.1.2
  3. Metro via Tétényi út to Astoria - alternative 3.1.3

Our conclusion was that all of the alternatives are relatively close and we consider they should all be evaluated in more detail in the short list.

  • Metro Line 2 Extension from Déli station to Kelenföld (3.4)

No reorganisation of services was considered for this alternative as the new extension served an area on the edge of the study area. To terminate existing tram services in this situation seemed unrealistic. The extension to Line 2 therefore provides an alternative route to the central area to those provided by existing trams.

Our conclusion was that the extension to line 2 is of limited passenger benefit and should not be taken forward.

  • Extension of the Metro Southwest to Budaörs area

In reviewing this extension, we noted that in itself this alternative is not competing against any other alignment but is a complementary scheme. Extending the metro line (any of the alternatives) to beyond the MÁV railway lines at Kelenföld is one that will be evaluated in Stage 2 of the Study. We had undertaken a preliminary assessment of this extension which identified that the impact of this extension on the different metro alignments east of Kelenföld is effectively identical. The number of passengers on the extension is unlikely to exceed 60,000 per day (both directions) producing modest benefits compared with the high costs of crossing the existing railway lines. The merits of extending the metro east of Kelenföld lie in the future scale of urban development in the Gazdagrét and Budaörs areas.