Previous Next


BUDAPEST METRO LINE 4 FEASIBILITY STUDY

Oktober 1996

Evaluation Of options

Outline of Methodology : Factors, objectives and the point allocation system

The short list evaluation is concerned with assessing each alternative against a range of planning, design, transport and environmental factors. This chapter is also concerned with comparing the performance of alternatives and choosing between them.

Chapter 7 outlined the design issues and costs of each alternative and Chapters 9 and 10 described their transport and economic benefits. This chapter brings together the economics with the planning, environmental and relevant design factors to assess the differences between the alternatives. The purpose of the evaluation process is to assist the decision making process - not to make the decision.

We had hoped to undertake a full quantification method applying weights to quantified impacts. At this stage such full quantification has not taken place and the environmental, planning and design factors, as described in the previous chapters, are evaluated in a subjective way. We have allocated points from 1-5 depending on how each alternative addresses the particular factor or objective. This is in order to assist us in comparing the alternatives. We do not consider it practical to add the points between factors due to the subjective nature of the analysis. Also this would imply that each factor was of equal importance. There are also not the same number of factors within each subject group and the analysis could therefore be biased.

Details of the point allocation are included within Stage 1 Report. The factors developed for the evaluation are as follows:

Economic Indicators
  • Total Costs
  • User Benefits
  • Road User Benefits
  • Accident Savings
  • Internal Rate of Return

The point system for the indicators expressed in monetary terms has been based on equal increments between the lowest and highest value ascribed to each factor. In each case the lowest and the highest value is assumed to be in the mid range of the point for that value.

Environment Impacts
  • Noise
  • Pollution
  • Vibration
  • Indirect impact
Planning Impacts

The following are the brief descriptions of the policies referred to in Chapter 4.

  • To support the overall development of Budapest as a world city and enhance city image.
  • To foster and support sustainable development whilst ensuring that an equal and positive range of opportunities is available to all.
  • To conserve and enhance the historical and cultural heritage and the natural environment within the City.
  • To implement overall land use / transportation strategies, maintaining the relative advantage of the city centre whilst supporting the provision of a more balanced pattern of land use and development within both the city and adjoining agglomerations.
  • To reduce current development pressures upon the established inner city areas by the selected focusing of growth and urban development upon the transition zone and main transport routes, more specifically by means of the establishment of new District and suburban centres.
  • To encourage economic development and regeneration, attracting new investment to the city, stimulating growth in leisure and tourism and restructuring and diversifying the present economic base, in particular within the transition zone.
  • To improve public transport systems, retain competitiveness and achieve appropriate modal splits within the various principal areas of the city.
  • To give priority to public transport within the inner city area, improve services in the suburban zone and support functional changes within the transition zone by developing transport services and contributing to an integrated transport system through the provision of interchange and park and ride facilities.
  • To support commercial and business activity and enhance access to leisure and cultural facilities by means of improved communications, providing an alternative to road usage, reducing road traffic congestion and improving the environment.

In terms of point allocations the majority of the impacts upon policies are in the range of neutral to positive. There are not likely to be significant negative impacts since all alternatives result in some level of investment and thereby improvement in the overall transport in the study area.

Design Impacts and Operation Impacts
  • Construction risks
  • Project risks
  • Impact of the construction works Duration of works
  • Possibility of phasing of the line
  • Flexibility of the system : related to the adaptability of the system

Evaluation

Our evaluation of Table 11.1 is described below for each alternative. The short list alternatives evaluated are as described in Chapter 9.

  • The Surface alternative

In overall terms we consider the surface alternative to be of limited value.

  • LRT alternatives

In overall terms alternatives 2.2.2.a. (via Fehérvári) is the preferred LRT alternative.

  • Comparison of LRT and Metro

The LRT alternative has significantly lower costs and in the next stage of the study we will examine aspects of the LRT system and in particular construction methods, rolling stock and operational characteristics as part of the cost optimisation process.

  • Metro alternatives

Our general conclusions based on urban planning issues may therefore be summarised as follows:

  1. Alternative 3.3.2 would provide an equivalent or better service to the main population catchment areas as compared to the Tétényi út or Bartók Béla alignments;
  2. the nature and extent of the likely development potential associated with and/or related to this alternative 3.3.2. is likely to exceed that of either of the two alternative alignments; and
  3. this alternative would be consistent with the overall aims and objectives of the emerging Budapest Master Plan and the strategy for the South West Corridor.

Conclusions

Our conclusions from Stage 1 of the study are presented below:

    From the background studies:

  1. The study Area has an existing and frequent public transport system comprising of buses and trams. The buses provide both local City services as well as longer distance services some of which terminate within the study Area. Some of the existing rolling stock is old and average operating speeds are relatively low.
  2. Such low speeds are partly a function of traffic congestion which is particularly heavy in the main tram corridors. This heavy flow of traffic contributes to traffic pollution in the study Area.
  3. The planning studies produced a set of objectives for assessing the transportation alternatives. These included impacts upon the transition zone, contribution towards economic development and assistance towards environmental goals by, in part, attracting traffic from roads.
  4. Option Development

  5. A number of alternatives were developed to address these issues including an improvement to existing surface modes, Light Rail schemes and Metros. We undertook a preliminary long list evaluation which concluded that:
    • on the Pest side the termination point for the Metro should be Keleti station. This was on the grounds that it opened up a further catchment area to the south of Rákóczi út and that the increase in benefits (in percentage terms) was greater than the higher costs compared to other alternatives.
    • the extension to Metro Line 2 from Déli station had poor benefits and contributed little to the south west corridor.
    • the extension of tram line 1, on the orbital route across Lágymányos bridge, could not be justified, attracting relatively low patronage levels.
    • the LRT over Erzsébet bridge was potentially damaging to the world heritage site, difficult in traffic terms and in economic terms, did not perform as well as the alternative crossing at Szabadság bridge.
    • we could not distinguish between the alternative alignments for either the Metro or LRT alternatives on the Buda side and further analysis was undertaken in the short list evaluation.

    Detailed Assessment

  6. The more detailed assessment of key planning issues produced a number of conclusions as follows:
    • that whatever public transport improvement proposals are taken forward in the South West Corridor, they must form an integral element of an overall land use/transportation strategy.
    • that any investment in Public Transport is generally positive in planning terms.
    • that alternatives with full segregation are likely to be more successful in achieving goals in modal split and transport integration.
    • routes using Fehérvári út are likely to have advantages in terms of closeness to the transition zone.
    • the traffic evaluation work demonstrated that the surface alternatives would do little to improving the already congested conditions on the streets. The Metro alternative had higher patronage attractions than the LRT and more extensively relieve existing services. This would provide more opportunity to consider surface level environmental improvements and development proposals. The Metro alignments attracted similar levels of patronage.

  7. From the economic evaluation we concluded that:
    • the surface mode alternative returned the lowest Benefit to Cost Ratio (BCR) ratio and Internal Rate of Return (IRR).
    • on the optimistic scenario for the LRT and Metro alternatives the BCR varied between 1.8 and 2.6 and the IRR between 8.3% and 10.3%.
    • on the pessimistic scenario for the LRT and Metro alternatives the BCR varied between 0.9 and 1.2 and the IRR between 6.5% and 8.3%.
    • the LRT alternatives had the highest economic returns with their lower benefits being offset by much lower levels of cost.
    • the Metro alternatives were very close in economic terms.
  8. In order to examine the alternatives we undertook a framework assessment bringing together all the relevant factors for comparison purposes. From this evaluation our conclusions are as follows :
    • the surface alternative is consistently ranked low
    • the preferred LRT alternative runs along Fehérvári út and compares favourably with some of the Metros.
    • the comparison of Metro alternatives shows only small economic differences, no differences in environmental terms and very similar performances in terms of design issues.
    • the choice between the Metro alternatives is determined principally upon the planning issues, but even here the differences are fine. However, in terms of providing both for a higher level service to an existing high density population and serving future potential developments, including the Transition zone on the west side of the Danube, then the alternative via Fehérvári has a number of advantages.

Achieving Stage 1, in accordance with the Steering Committee representatives, the metro alternative Tétényi (3.3.3) was preferred by the Municipality of Budapest to be refined in the course of Stage 2.