Previous Next


BUDAPEST METRO LINE 4 FEASIBILITY STUDY

Oktober 1996

Economic Analysis

This chapter sets out the methodology and key parameters and the results of the economic evaluation of the short list alternatives examined.

Overview and assumptions for the economic evaluation

The economic evaluation is concerned with comparing alternatives in terms of their overall resource costs to society independent of the incidence of costs (and benefits) to specific groups or organisations.

  1. The evaluation covered:
  2. Capital costs for the public transport system, principally:
    1. land and infrastructure
    2. public transport rolling stock
  3. Operating and maintenance costs for the public transport system (all modes)
  4. Benefits to public transport and highway users

The economic evaluation was not concerned with revenues, which are not resource costs but represent a transfer payment between public transport operators and users. Similarly the evaluation excluded taxation components and inflation effects from the costs and benefits.

The evaluation was concerned principally with the differences between alternatives. It was therefore essential to ensure that the inputs to the costing and evaluation are consistent between alternatives.

The geographical area covered by the evaluation for this study was sufficient to cover all significant changes in transport demand and supply patterns associated with the various alternatives as a Budapest-wide network was used for the purposes of transport modelling and assessing user benefits, as discussed in Chapter 6.

To assess the merits of public transport in the corridor, a 'Do Minimum' option was defined against which 'Do-something' options could be compared. A description of the Do Minimum scenario is included in Chapter 9. Details of the short list of 'Do-something' alternatives and their respective passenger forecasts is included in Chapter 9.

Key evaluation input parameters
  • Currency

Economic evaluation results are expressed in ECU. The majority of the analysis was undertaken in Hungarian Forints which was converted to ECU based on a currency exchange rate of 185.3 Forints to 1ECU as a representative exchange rate for first quarter of 1996.

  • Discount rates

For stage 1 evaluations we have adopted discount rates of 5% and 7%.

  • National growth rates

Following discussions with the Study Steering Committee two sets of growth rates were used to reflect the high and low growth assumptions. These are as follows:

Table 10.1. Growth Rates for Low & High Scenarios

present to 2000
2000 to 2020
Beyond 2020
Low growth assumptions
3%
4%
2%
High growth assumptions
3%
6%
3%


  • Evaluation period

The evaluation period adopted covered the period of project construction plus a benefit period of 40 years from the start of operation of the alternative.

  • Start year

It was assumed that all alternatives would start operation in January 2005, i.e. the 40 year evaluation period would cover years 2005 - 2044 (inclusive). LRT and metro options are assumed to be constructed over a 4 year period (2001 - 2004).

  • Base year for pricing and discounting

All prices have been related to the same base period (i.e. adjusted for inflation). 1996 has been used for this purpose. Year 1996 was also used as the base to which costs and benefits were discounted.

  • Value of time

Public transport passengers

Value of time for public transport passengers was calculated as 40% of gross average wage rate. Wage rates used were based on the most recent data from the Hungarian Central Statistics Office which was for 1995 and was rebased to 1996 to 149 Hungarian Forint.

Private vehicle driver and passenger

For private vehicle driver and passengers, public transport passenger's value of time was increased by 20% (to 179 Forints) to allow for the higher proportion of business travel by private vehicle occupants.

  • Private vehicle occupancy

Based on the results of the analysis undertaken on data from Budapest General Transport Surveys (1992-1994) a value of 1.4 occupants per vehicle was adopted.

  • Private vehicle accident rates

Based on an analysis of local accident statistics between 1990 and 1995 (inclusive) an average accident rate of 131.32 accidents per 100 million vehicle kilometres was adopted across all severities.

  • Private vehicle accident cost

Based on disaggregated accident costs data made available by local consultants which is widely used in Hungary, a weighted average (across all severities) accident cost of 1.573 Million Forints per accident was adopted.

  • Private vehicle maintenance operating and capital cost

Based on disaggregated private vehicle operating and maintenance costs data for urban private vehicle use, made available by local consultants and which is widely used in Budapest, an average overall maintenance, operating and capital cost of 15.28 Forints per vehicle kilometre was adopted.

  • Conversion from peak hour to annual

Based on the results of the analysis undertaken on data from Budapest General Transport Surveys (1992-1994) for both public transport and highway traffic and discussions with Budapest public transport operator company (BKV) a peak hour to all day conversion factor of 13 and daily to annual conversion factor of 300 was adopted.

Key evaluation output criteria

Key evaluation outputs which have been used to assess the relative merits of the various alternatives are:

  1. Net Present Value (NPV) : Sum of discounted costs less Sum of discounted benefits
  2. Benefit to Cost Ratio (BCR) : Sum of discounted benefits divided by Sum of discounted capital costs
  3. Internal Rate of Return (IRR) : Discount rate at which the project cash flow produces a zero NPV.

Infrastructure and Rolling Stock Costs

Land and Infrastructure

The derivation of these costs have been described in detail in Chapter 7. For the purposes of economic assessments net infrastructure costs of the scheme are considered. This is the cost of construction of the scheme less any costs which would incur in the Do Minimum scenario. For this study, Do Minimum costs are only applicable for the strengthening of Szabadság bridge to allow the continuation of operation of tram routes 47 and 49. This cost is estimated at 19 Million ECU. The cost of the tram track rehabilitation programme is not included as its implementation is not influenced by the schemes being considered here.

A summary of land and infrastructure costs for the short list alternatives being considered is as follows:

Table 10.2. Summary of infrastructure costs

Alternative
Million ECU *
Overall improvement of existing surface modes 1.3
121
LRT via Bartók to Astoria over Szabadság 2.2.1.a
245
LRT via Fehérvári to Astoria over Szabadság 2.2.2.a
275
Metro via Bartók/ Rákóczi to Keleti 3.3.1
426
Metro via Fehérvári/ Rákóczi to Keleti 3.3.2
473
Metro via Tétényi/ Rákóczi to Keleti 3.3.3
447

* Above costs include land costs design supervision and contingencies

All costs are in undiscounted 1996 prices, in Million ECU

It has been assumed that the construction period is 4 years starting in 2001 and expenditure attributed to each year of construction will be 15%, 20%, 35% and 30% from year 1 to year 4 respectively.

Residual value of both land and infrastructure at the end of evaluation period will be small and has been ignored.

Public Transport Rolling Stock costs

Capital costs and related information for public transport vehicles were derived from a number of sources including estimates provided to the study team by BKV and study team's knowledge of similar work in France, UK and elsewhere both in 'western' and 'eastern' Europe. Table 10.3 summarises the vehicle costs for replacing existing vehicle stock adopted for the study.

3. Existing vehicle rolling stock costs

Mode
Cost/Vehicle *
(Million HuF)
% Spares: Peak Vehicles
Cost/Peak Vehicle (Million HuF)
Vehicle
Capacity †
Cost/Peak Place (Million HuF)
Tram
Capacity 200 180 25225200 1.125
Capacity 283 254** 25318283 1.125
Capacity 400 360¤¤ 25450400 1.125
Bus
Artic.29 2536.25120 0.302
Standard20 2525.0068 0.368
Metro ¤¤
M1157 15180189 0.952
M2692 15796890 0.895
M3854 159821098 0.895

* 'Vehicle' refers to a full train-set.

† Based on 5 passengers per m2

** Costs assumed pro rata to capacity based on 200 place trams

¤¤ Costs assumed pro rata to capacity based on BKV estimates (mid-point)

Key points of note include:

  • Loading criteria

All vehicle capacities have been based on the loading standard of 5 persons/m2 (i.e. all seats occupied and 5 standees per m2 of standing area). However, following discussions with BKV it was agreed that for this stage of the study, for service planning purposes 80% of the above capacity would be adopted (i.e. 4 persons per m2). Therefore all capacities are based on 4 persons/m2.

  • Existing metro vehicles

BKV provided costs for metro cars ranging from 96 Million HuF (0.52 Million ECU) per car representing vehicles generally similar to those currently operated to 200 Million HuF (1.08 Million ECU) per car which in BKV's view reflects modern Metro specifications similar to those used in Western Europe. For the Stage 1 evaluation, the mid-point of this range, 148 Million HuF (0.8 Million ECU) per car has been used for replacing existing rolling stock where necessary on the existing metro lines.

An average capacity of 190 passengers has been adopted for each existing metro car based on 5 passengers/m2. Spares required for metro trains are assumed at 15% of the operational rolling stock and lives are assumed at 40 years.

  • Existing trams

Based on data provided by BKV existing tram vehicle (train-set) costs range from 180 Million HuF (0.97 Million ECU) for the smallest vehicle with a capacity of 200 passengers to 360 Million HuF (1.94 Million ECU) with a capacity of 400 passengers. These values were adopted for the assessment based on the type of tram which needed replacement. Spares required for existing tram trains are assumed at 25% and lives are assumed at 30 years.

  • Existing Diesel buses

Data for two types of buses was analysed and used for the assessment. These were articulated buses with a capacity of 120 passengers costing 29 Million HuF (0.16 Million ECU) and standard buses with a capacity of 68 passengers for 20 Million HuF (0.11 Million ECU). Spares required for existing diesel buses are assumed at 25% and lives are assumed at 15 years.

  • Existing trolley buses

Data for two types of trolley buses was analysed and used for the assessment. These were articulated and standard trolleys with capacity of 114 and 68 passengers costing 54 Million HuF (0.29 Million ECU) and 45 Million HuF (0.24 Million ECU) respectively. Spares required for existing trolley buses are assumed at 25% and lives are assumed at 15 years.

  • New rolling stock

Chapter 7 provided a set of realistic ranges of costs for new metro LRT and tram vehicles. Based on figures in Table 7.1 we have adopted rolling stock cost values to use with this assessment. Adopted figures are generally mid-point of figures in Table 7.1. Table 10.4 presents a summary of the cost values adopted for new vehicles. New metro and LRT vehicles are assumed to have a life of 40 years with spares assumed at 15%. Lives for new trams is assumed as 30 years with a proportion of spares of 15%.

Table 10.4. Costs for new rolling stock

Mode
Cost/Vehicle

(Million HuF)
% Spares:

Peak Vehicles
Cost/Peak

Vehicle

(Million HuF)
Vehicle

Capacity * *
Cost/Peak

Place

(Million HuF)
Tram
New tram veh.232 15265240 1.104
1 car train-set
LRT
Train-set of 1 112 151 279750 1.710
3 cars
Metro
Train-set of 1 110 151 2781025 1.247
5 cars

* Based on 5 passengers per m2

Vehicle residual values have been estimated consistent with the lives assumed. (The assumptions on residual values will have only slight effects on the evaluation results).

Unit Operating and Maintenance Costs

Unit operating and maintenance costs for each mode (bus trolley tram metro LRT) were derived and averaged per capacity kilometre based primarily on BKV actual cost data with certain adjustments. Costs in this case related to "working expenses" only i.e. excluding any capital charges (amortisation etc) associated with vehicles and infrastructure which is discussed in the next section of this chapter.

The steps in the process of deriving these costs were detailed in Stage 1 Report and the results are summarised in Tables 10.5 & 6..

Table 10.5. Average Operating Cost Estimates based on BKV data

Costs (*) in HuF per 1000 Capacity Km

Mode/Vehicle Type

1991
Factor

1991 - 1994

1994
Tram
UV 2 Twin797.2 926.8
UV 3 Twin673.0 782.4
Artic778.3 904.9
Artic Twin733.5 852.8
Tatra Twin731.8 850.8
Tatra 3 Unit706.7 821.6
Total736.1 1.1626855.8
Trolleybus
ZIU - 91070.1 1255.4
Ganz781.7 917.0
Total909.7 1.17311067.2
Bus
Diesel
1K 260770.5 1053.5
1K 280583.2 797.4
1K 415904.2 1236.3
Total674.2 1.3673921.8
Metro
Line 1838.4 1071.0
Line 2537.0 686.0
Line 3430.0 549.3
Total481.6 1.2774615.2

* Figures exclude amortisation

Table 10.6. Unit Operating Costs Adopted for Assessments

1994 Typical
1996 Typical
Values Adopted
Mode
Values
Values
for Assessment *
Tram
800
920
900
Bus
800
920
900
Metro
550
632
550 **
LRT
-
-
650

* All costs are in HuF per 1000 Capacity kilometre (Excluding vehicle and infrastructure amortisation

** Assumes modern vehicles with some operating/maintenance efficiency improvements

Application of unit operating and vehicle capital costs

For each alternative (relative to the Do Minimum), the incremental vehicle requirements and operating statistics were estimated and hence, by applying the unit costs, the incremental vehicle capital and annual operating costs were calculated. The methods covered all the services whose patronage might be significantly affected by any alternatives. Different methods, detailed within Stage 1 Report, were used for bus and Tram services than those used for Metro/LRT services.

Benefits

Total benefit to travellers is calculated based on four main categories as follows:

  1. Public transport user benefits
  2. Decongestion benefits to private vehicle users
  3. Vehicle operating and capital cost savings to private vehicle users
  4. Accident savings to private vehicle and other highway users

Methodology for calculating each of the above categories is explained as follows:

Public transport user benefits

User benefits have been calculated directly from the demand modelling work as the difference in generalised costs (excluding fare) between the Do Minimum and each alternative. This is the same data that is used to calculate the public transport sub-mode split and assignment. Total difference in generalised costs (excluding fare) is extracted from the public transport model and the value of time is applied to these time savings. Furthermore, there are benefits which are attributed to the generated traffic based on the 'rule-of-the-half' which are included in the overall public transport user benefits. These benefits are applied to the generated public transport passengers, regardless of whether they arise from mode transfers, trip redistribution or increases in trip-making.

Decongestion benefits to private vehicle users

To assess the benefit to private vehicle drivers and passengers a capacity restrained urban highway model of Budapest was used. Generated trips were estimated based on the 'elasticised matrix' methodology (described in Chapter 9). Some 30% of the generated demand was assumed to be the result of mode switch from the private vehicles. This incorporated the traffic growth rates discussed in Chapter 9. Based on this calculation the private vehicle matrix was adjusted and the highway model was re-run to establish the time savings incurred to the remaining traffic on the highway. These time savings were incorporated in the total benefits as savings attributed to the private vehicle users due to decongestion resulting from the alternative being considered.

Vehicle operating and capital cost savings to private vehicle users

Estimation of vehicle operating and capital cost savings were based on the reduction in private vehicle kilometres obtained from highway model runs as described above. A unit operating and capital cost per vehicle kilometre (described earlier in this chapter) was applied to the reduction in total vehicle kilometres and incorporated in the overall savings/benefits of the alternatives.

Accident benefits to private vehicle and other highway users

Using the output from the highway model runs giving the total savings in vehicle kilometres the unit average accident cost (across all severities) was applied to estimate the accident benefits.

Results of the economic analysis

Infrastructure

Infrastructure costs input to the economic analysis are the net cost of the alternative being considered, i.e. the full cost of construction, land, design supervision and contingencies less the cost of the Do Minimum scenario which is the cost of strengthening Szabadság bridge estimated at 19 Million ECU. Table 10.7 presents a summary of infrastructure costs at 1996 prices and discounted to 1996.

Table 10.7. Summary of infrastructure costs

(Costs are in 1996 Million ECU) *

Alternative

Total

Costs
Do Minimum

Costs
Net Costs

(undiscounted)
Net Costs

(discounted at 5%)
Net Costs

(discounted at 7%)
Improve. surface modes 1.3
121
19
102
72.57
63.91
LRT via Bartók 2.2.1.a
245
19
226
162.40
143.01
LRT via Fehérvári 2.2.2.a
275
19
256
183.95
161.99
Metro via Bartók 3.3.1
426
19
407
292.45
257.54
Metro via Fehérvári 3.3.2
473
19
454
326.23
287.28
Metro via Tétényi 3.3.3
447
19
428
307.54
270.83

* Above costs include land costs design supervision and contingencies


The lowest cost alternative is the improvement of the surface modes and the most expensive alternative is the Metro via Fehérvári út due to its longer length.

Rolling stock operating and maintenance costs

For the purposes of the economic assessment, vehicle capital and operating costs for each alternative is calculated against the savings which arise due to the relief given to existing services. The results of the estimation of net vehicle capital and operating costs of the alternatives in 2020 is presented in Table 10.8. The operating costs show are appropriate for the one year whilst the capital costs would be spread over the project life.

Table 10.8. Summary of undiscounted net P.T. vehicle capital and operating costs

Tram
Bus
Existing Metro
Total Existing modes
New mode
Overall total
Alternative *
Capital
Oper.
Capital
Oper.
Capital
Oper.
Capital
Oper.
Capital
Oper.
Capital
Oper.
Improve Existing 1.3 53.26 0.76-1.03 -0.27 0-0.12 52.24 0.370 052.24 0.37
LRT via Bartók 2.2.1a -86.95 -4.80-5.58 -1.48 9.600.35 -82.94 -5.93131.25 4.05 48.31-1.88
LRT via Fehérvári 2.2.2a -98.89 -5.46-6.25 -1.66 9.600.48 -95.54 -6.64158.88 5.04 63.34-1.60
Metro via Bartók 3.3.1 -53.97 -2.98-9.21 -2.44 5.36-0.21 -57.82 -5.63123.95 4.66 48.31-0.97
Metro via Fehérvári 3.3.2 -59.06 -3.26-9.78 -2.59 5.36-0.12 -63.48 -5.97130.84 5.37 67.36-0.60
Metro via Tétényi 3.3.3 -57.16 -3.16-9.60 -2.55 5.36-0.18 -61.40 -5.89130.84 5.03 69.44-0.86

* All values are based on 2020 forecast passenger levels

All values are undiscounted 1996 values in Million ECU

Negative values denote savings on operation / vehicle capital

Table 10.8 shows that in general overall savings can be expected in operating costs for all the alternatives with the exception of the improvement of existing surface modes.

Benefits

Total benefits resulting from any of the evaluated alternatives are made up of 4 sources as discussed in section 10.4 above.

Table 10.9 presents a summary of the benefits over the assessment period in undiscounted 1996 values and Tables 10.10 and 10.1. present a summary of discounted benefits based for high and low growth scenarios respectively.

Table 10.9. Summary of undiscounted benefits over the assessment period

High growth scenario
P.T. Pass. Benefits
Accident Savings
Decongest. Benefits
Priv. Veh. Savings
Total benefits
Alternative *
Undiscounted
Undiscounted
Undiscounted
Undiscounted
Undiscounted
Surface mode improv. 1.3 475.10 8.33106.84 17.26 607.53
78% 1%18% 3%100%
LRT via Bartók 2.2.1a 1294.82 24.84289.11 44.69 1653.46
78% 2%17% 3%100%
LRT via Fehérvári 2.2.2a 1623.95 32.45388.65 60.91 2105.94
77% 2%18% 3%100%
Metro via Bartók 3.3.1 2089.41 41.04486.51 75.87 2692.84
78% 2%18% 3%100%
Metro via Fehérvári 3.3.2 2207.74 44.47528.75 82.58 2863.54
77% 2%18% 3%100%
Metro via Tétényi 3.3.3 2057.27 40.28478.02 74.59 2650.16
78% 2%18% 3%100%
Low growth scenario
P.T. Pass. Benefits
Accident Savings
Decongest. Benefits
Priv. Veh. Savings
Total benefits
Alternative
Undiscounted
Undiscounted
Undiscounted
Undiscounted
Undiscounted
Improvement of existing surface modes 1.3 305.88 5.5672.10 17.26 400.80
76% 1%18% 4%100%
LRT via Bartók 2.2.1a 848.00 16.09191.85 44.69 1100.63
77% 1%17% 4%100%
LRT via Fehérvári 2.2.2a 1059.80 21.19259.24 60.91 1401.14
76% 2%19% 4%100%
Metro via Bartók 3.3.1 1360.29 26.72323.91 75.87 1786.80
76% 1%18% 4%100%
Metro via Fehérvári 3.3.2 1435.31 28.98352.23 82.58 1899.10
76% 2%19% 4%100%
Metro via Tétényi 3.3.3 1338.78 26.24318.33 74.59 1757.93
76% 1%18% 4%100%

* All figures are undiscounted 1996 values in 1000 ECU

Percentages shown are proportions of total benefits

Table 10.10. Breakdown of discounted benefits for High Growth Scenario

Discount Rate: 5%

Alternative *
P.T. Pass. Benefits
Accident Savings
Decongest. Benefits
Priv. Veh. Savings
Total Benefits
Surface mode improv. 1.3 107.82 1.8523.57 4.63 137.87
78% 1%17% 3%100%
LRT via Bartók 2.2.1a 290.90 5.6264.47 12.62 373.58
78% 2%17% 3%100%
LRT via Fehérvári 2.2.2a 365.61 7.3086.39 16.93 476.20
77% 2%18% 4%100%
Metro via Bartók 3.3.1 471.08 9.25108.27 21.21 609.77
77% 2%18% 3%100%
Metro via Fehérvári 3.3.2 498.17 10.02117.62 23.05 648.82
77% 2%18% 4%100%
Metro via Tétényi 3.3.3 463.95 9.08106.36 20.84 600.19
77% 2%18% 3%100%
Discount Rate: 7%

Alternative *
P.T. Pass. Benefits
Accident Savings
Decongest. Benefits
Priv. Veh. Savings
Total benefits
Surface mode improv. 1.3 65.69 1.1114.16 3.00 83.95
78% 1%17% 4%100%
LRT via Bartók 2.2.1a 176.34 3.4238.95 8.34 227.00
78% 2%17% 4%100%
LRT via Fehérvári 2.2.2a 221.86 4.4352.10 11.12 289.45
77% 2%18% 4%100%
Metro via Bartók 3.3.1 286.06 5.6265.34 13.96 370.91
77% 2%18% 4%100%
Metro via Fehérvári 3.3.2 302.64 6.0870.98 15.16 394.78
77% 2%18% 4%100%
Metro via Tétényi 3.3.3 281.77 5.5164.19 13.71 365.11
77% 2%18% 4%100%

* All figures are in discounted 1996 values, Million ECU

Percentages shown are proportions of total benefits

Table 10.11. Breakdown of discounted benefits for Low Growth Scenario

Discount Rate: 5%

Alternative *
P.T. Pass. Benefits
Accident Savings
Decongest. Benefits
Priv. Veh. Savings
Total Benefits
Surface mode improv. 1.3 74.75 1.3216.93 4.63 97.64
77% 1%17% 5%100%
LRT via Bartók 2.2.1a 204.26 3.9145.73 12.62 266.50
77% 1%17% 5%100%
LRT via Fehérvári 2.2.2a 256.05 5.1261.51 16.93 339.58
75% 2%18% 5%100%
Metro via Bartók 3.3.1 329.32 6.4776.98 21.21 433.94
76% 1%18% 5%100%
Metro via Fehérvári 3.3.2 347.89 7.0183.67 23.05 461.58
75% 2%18% 5%100%
Metro via Tétényi 3.3.3 324.23 6.3575.64 20.84 427.02
76% 1%18% 5%100%
Discount Rate: 7%

Alternative *
P.T. Pass. Benefits
Accident Savings
Decongest. Benefits
Priv. Veh. Savings
Total benefits
Surface mode improv. 1.3 46.90 0.8110.43 3.00 61.13
77% 1%17% 5%100%
LRT via Bartók 2.2.1a 127.28 2.4528.37 8.34 166.40
76% 1%17% 5%100%
LRT via Fehérvári 2.2.2a 159.78 3.1938.08 11.12 212.11
75% 2%18% 5%100%
Metro via Bartók 3.3.1 205.69 4.0447.69 13.96 271.32
76% 1%18% 5%100%
Metro via Fehérvári 3.3.2 217.42 4.3851.82 15.16 288.71
75% 2%18% 5%100%
Metro via Tétényi 3.3.3 202.55 3.9646.86 13.71 267.02
76% 1%18% 5%100%

* All figures are in discounted 1996 values, in Million ECU

Percentages shown are proportions of total benefits

Metro alternatives in general result in the highest benefits, particularly for the public transport passenger benefits. The incremental increase of benefits of metro alternatives over the LRT alternatives is due to the larger catchment area of metro alternatives on the Pest side (metro alternatives terminate at Keleti station whereas LRT alternatives terminate at Astoria).

Overall economic performance

Tables 10.12 and 10.13 present a summary of the economic evaluation results for the two test discount rates and the high and low growth scenarios.

LRT alignment via Fehérvári út produces the best Internal Rate of Return for both high and low growth scenario (10.3% and 8.3% respectively). All metro alternatives produce similar IRR values ranging from 8.3% (for alignment via Tétényi) and 8.8% (for alignment via Bartók Béla út) in the high growth scenario and 6.5% to 6.9% in the low growth scenario. Ranking of metro alignments based on the IRR is consistent across low and high growth scenarios with only marginal differences between alternatives. Given the accuracy of the travel model the conclusion would therefore be that on the basis of Internal Rate of Return criteria all metro alternatives perform equally as well.

In Net Present Value terms, again the performances of the metro alignments are very close with the alignment via Bartók Béla consistently performing better (albeit marginally) than the other two alignments. Taking the best economic scenario (high growth with the lowest test discount rate of 5%) the alignment via Bartók Béla út returns a NPV of 301 Million ECU, Fehérvári út returns a NPV of 299 Million ECU, and Tétényi returns a NPV of 272 Million ECU. Again these differences should generally be considered.

Benefit to Cost Ratios provide a similar picture with Bartók Béla alignment producing a ratio of 1.98, Fehérvári alignment, 1.86 and Tétényi alignment producing a benefit to cost ratio of 1.83, with the high growth assumption and the lowest test discount rate of 5%.

It is therefore concluded that:

  1. the LRT alternative via Fehérvári út consistently produces the best economic returns which in fact improves with the lower growth assumptions and more stringent test discount rates.
  2. comparison within the metro alternative category shows similar performances for all alignments.

Table 10.12. Summary of economic evaluation for High growth scenario

Discount Rate: 5%
Costs
Benefit

Alternative *
Const.
Veh. Cap.
Op. & Main.
Benefits
NPV
to Cost

Ratio
IRR
Surface mode improv. 1.3 72.57 30.36 7.19 137.87 27.71.25 6.2%
LRT via Bartók 2.2.1a 162.40 24.85 -36.52 373.58 222.92.48 9.8%
LRT via Fehérvári 2.2.2a 183.95 32.17 -32.09 476.20 292.22.59 10.3%
Metro via Bartók 3.3.1 292.45 35.54 -19.58 609.77 301.31.98 8.8%
Metro via Fehérvári 3.3.2 326.23 36.39 -13.00 648.82 299.21.86 8.5%
Metro via Tétényi 3.3.3 307.54 37.90 -17.66 600.19 272.41.83 8.3%
Discount Rate: 7%
Costs
Benefit

Alternative *
Const.
Veh. Cap.
Op. & Main.
Benefits
NPV
to Cost

Ratio
IRR
Surface mode improv. 1.3 63.91 25.43 4.48 83.95 -9.90.89 6.2%
LRT via Bartók 2.2.1a 143.01 21.89 -22.74 227.00 84.81.60 9.8%
LRT via Fehérvári 2.2.2a 161.99 28.23 -20.02 289.45 119.21.70 10.3%
Metro via Bartók 3.3.1 257.54 31.08 -12.22 370.91 94.51.34 8.8%
Metro via Fehérvári 3.3.2 287.28 31.87 -8.14 394.78 83.81.27 8.5%
Metro via Tétényi 3.3.3 270.83 33.13 -11.03 365.11 72.21.25 8.3%

* All figures are in discounted 1996 values, in Million ECU

Negative operating and maintenance cost values denote savings

Value of Internal Rate of Return is independent of the test discount rate

Table 10.13. Summary of economic evaluation for Low growth scenario

Discount Rate: 5%
Costs
Benefit
Alternative *
Const.
Veh. Cap.
Op. & Main.
Benefits
NPV
to Cost

Ratio
IRR
Surface mode improv. 1.3 72.57 30.36 5.97 97.64 -11.30.90 4.3%
LRT via Bartók 2.2.1a 162.40 24.85 -30.33 266.50 109.61.70 7.9%
LRT via Fehérvári 2.2.2a 183.95 32.17 -26.58 339.58 150.01.79 8.3%
Metro via Bartók 3.3.1 292.45 35.54 -16.20 433.94 122.11.39 6.9%
Metro via Fehérvári 3.3.2 326.23 36.39 -10.69 461.58 109.71.31 6.6%
Metro via Tétényi 3.3.3 307.54 37.90 -14.59 427.02 96.21.29 6.5%
Discount Rate: 7%
Costs
Benefit
Alternative *
Const.
Veh. Cap.
Op. & Main.
Benefits
NPV
to Cost

Ratio
IRR
Surface mode improv. 1.3 63.91 25.43 3.77 61.13 -32.00.66 4.3%
LRT via Bartók 2.2.1a 143.01 21.89 -19.13 166.40 20.61.14 7.9%
LRT via Fehérvári 2.2.2a 161.99 28.23 -16.80 212.11 38.71.22 8.3%
Metro via Bartók 3.3.1 257.54 31.08 -10.25 271.32 -7.10.97 6.9%
Metro via Fehérvári 3.3.2 287.28 31.87 -6.79 288.71 -23.60.92 6.6%
Metro via Tétényi 3.3.3 270.83 33.13 -9.24 267.02 -27.70.91 6.5%

* All figures are in discounted 1996 values, in Million ECU

Negative operating and maintenance cost values denote savings

Value of Internal Rate of Return is independent of the test discount rate