Previous Next


BUDAPEST METRO LINE 4 FEASIBILITY STUDY

Oktober 1996

Environmental assessment

The environmental assessment was limited to a preliminary qualitative assessment. Two main issues are taken into consideration:

  1. Environmental impacts related to noise, air pollution and vibrations
  2. Environmental impacts related to the urban fabric, excluding the works period.

Environmental impacts related to noise, AIR Pollution and vibrations

For this comparative stage of the study, it is assumed that :

  1. There is not any significant change between the « Do Minimum » option and Option 1 -- Surface modes in terms of environmental impacts: it is presumed that the level of air pollution and noise should be stable. The air pollution and level of noise are likely to increase because of the increase of car traffic congestion.
  2. There is no significant difference between Underground LRT alternatives and Metro underground alternatives: they should contribute to very slightly decreasing the air pollution and level of noise.
  3. Considering the partly at-grade alternatives, they should slightly decrease the air pollution, the level noise and the level of vibration, due partly to the electric power supply and partly to the new technical characteristics of the rolling stock.

Environmental impacts related to the urban fabric.

A preliminary site reconnaissance had been performed, so as to assess the urban fabric and the impact on the historical heritage and urban facilities.

The site reconnaissance concerns mainly the following streets, avenues and squares, namely:

  1. on the Pest side, Szabad sajto út, Ferenciek Square, Kossuth Lajos út, Karoly krt, Muzeum krt, Kálvin Square, Vamhaz krt
  2. on the Buda side, Szt Gellért rkp, Szt Gellért Square, Bartók Béla út, Móricz Zs körter, Kosztolányi Dezsó Square, Vasut út, Etele Square, Etele út, Tétényi út, Fehérvári út, Bocskai út, Október 23 út.

Option 1 - Surface modes

The existing situation should be worsened, due to higher frequency of buses and tram and the related 'visual' intrusion.

Option 2 - LRT

The LRT Erzsébet alternatives 2.1 generate the worst impacts: they would interfere with protected areas of historical heritage, in terms of visual intrusion and poor urban integration in the city centre. They would partly demolish some buildings at Kossuth Lajos út especially. Even if some arcades are provided to improve the implementation, urban severance would be high.

The LRT over Szabadság alternatives 2.2.1.a and 2.2.2.a would induce impacts mainly in crossing over the bridge. They impact could be appreciated as either positive or negative, depending on the architectural integration and adjoining measures.

Option 3 - Metro

This option should not generate any direct impact on the urban fabric.

Future demand forecast

Introduction

A description of long list alternatives and the process of short listing was discussed in Chapter 6. The long list alternatives were examined according to the transport and economic criteria defined in Chapter 6, the engineering and preliminary environmental criteria described in Chapters 7 and 8. From that long list, the short listed alternatives being evaluated in the course of the detailed assessment were as follows:

Alternative 1.3 Overall improvement of existing surface modes

Alternative 2.2.1.a LRT via Bartók to Astoria over Szabadság

Alternative 2.2.2.a LRT via Fehérvári to Astoria over Szabadság

Alternative 3.3.1 Metro via Bartók/Rákóczi to Keleti

Alternative 3.3.2 Metro via Fehérvári/ Rákóczi to Keleti

Alternative 3.3.3 Metro via Tétényi/ Rákóczi to Keleti

Construction and calibration of the base transport model of Budapest was discussed in Chapter 3 of this report. The forecasting process builds upon the base transport model. For the purposes of forecasting, the base network is updated based on planned improvements and according to the alternative specified. The base demand matrix is factored based upon assumptions in the growth of passenger demand within the corridor of interest.

This chapter reports on the work undertaken and the assumptions made to produce the future demand forecasts for this study.

Components of the forecasting process

The future level of patronage on a transport facility is related to two principal factors: passenger demand and future transport networks, as follows:

Passenger demand

Urban planning factors

These factors reflect projections of population, employment and commercial activity for the medium and long term. Based on these factors a number of projections of the growth in passengers have been developed. For the purposes of this study one central case was taken forward based on an acceptable and reasonable population and employment forecast and planned development proposals in the corridor of interest. The projection used detailed planning within the study area. For other areas, the information provided is at District level.

It is to be noted that the degree of certainty which can be attached to the Budapest Master Plan policies and proposals has proved at this stage to be less robust than was anticipated at the study outset. In addition, it has been confirmed as one of the outcomes from our studies that a far closer integration between land use planning and development and public transport systems proposals will be required within the Southwest Corridor than presently exists if the preferred option for system improvement (whether Metro or an alternative scheme) is to be fully supported, consistent with Master Plan and Transport Development Plan objectives.

Population

The initial population forecasts produced anticipated that population levels would decrease by some 15% between 1994 and 2020. This forecast was based on the assumption that current high mortality rates would continue, such that average life expectancy was forecast to rise very slowly, by about 2.9 years over the 30 years from 1990 to 2020.

This assumption has been carefully examined and average life expectancy data in 10 'Western' European countries since the 1950's has been reviewed. This shows that those countries in Northern Europe have typically increased their life expectancies by 5-7 years and Southern European countries by some 10 years. Given an expanding economy and subsequent membership of the EU, it is postulated that life expectancy in Hungary will increase in a similar fashion.

Furthermore other independent data and analysis obtained from other sources providing Budapest and Agglomerations population forecasts to 2020 shows that population levels are forecast to remain constant over time.

Population forecasting is obviously an area of debate, but for the purposes of this project, it has been assumed that population levels in Budapest will remain constant over time. Population forecasts at a detailed level have therefore been produced and then controlled to an overall zero growth rate for Budapest, as follows:

  1. outside of the Study Area, sector level (9 sectors in Budapest) growth rates have been applied to District Level 1994 populations;
  2. in the Study Area (excluding District XI), District level (8 Districts in the Study Area) growth rates have been applied to District 1994 populations;
  3. within District XI, City Planning Unit (CPU) level (42 CPUs) growth rates have been applied taking into account the specific development opportunities identified; and
  4. forecasts have been produced for each of the 5 rural communities, adjusted in line with zero growth overall for Budapest.

The resultant population forecasts are summarised in Table 9.1 below. The study area population total is shown to decline slightly over time, but with District XI increasing by up to 10% by year 2020.

Table 9.1. Summary of Population Forecasts

(All figures are in 1000s)
1994
2020 High
Budapest1 9961 996
Study Area596586
District XI167184
South West Rural Areas* 87 102

* South West Rural Areas include Érd, Budaörs, Budakeszi, Törökbálint and Diósd.


Employment

Central Statistical Office employment data and information on commuting patterns have been used to derive base year (1994) employment levels by District. The District XI employment has been disaggregated to City Planning Unit (CPU) levels (42 CPUs in total) based upon the residential employment within each CPU. This assumes that a CPU with a high level of residential employment will also have a high level of commuting. Future year employment levels are estimated by applying growth rates to the base year employment level as follows:

  1. outside of the study area at sector level (9 sectors);
  2. within the study area at District level taking into account the specific development opportunities identified;
  3. within District XI at the 42 CPU level taking into account the specific development opportunities identified.

Forecasts which were taken forward to the demand forecasting stage were produced for 2020 for a central growth scenario. Resultant employment forecasts are summarised in Table 9.2 below. An overall decline in total employment numbers for Budapest is anticipated of some 8% by 2020. In District XI however, employment is forecast to increase by up to 22% by year 2020 based on the development potential identified, discussed later in this chapter.

Table 9.2. Summary of Employment Forecasts

(All figures are in 1000s)
1994
2020
Budapest981907
Study Area486525
District XI86105
South West Rural Areas *31 58

* South West Rural Areas include Erd, Budaörs, Budakeszi, Törökbálint and Diósd.

Development Potential in the study area

In addition to the likely influences of prospective EU membership, an expanding economy and gradually increasing life expectancy as identified above, a number of other key factors are relevant to any consideration of employment/population forecasts for the study area and have been taken into account in the preparation of the future year scenario. Within the South West corridor these include:

  1. on-going developments in Districts XI and XXII which are attracting younger, well qualified people to the area;
  2. the traditional pull of institutional, administrational and educational establishments within the corridor; and
  3. the emergence of the Western Gate - Kelenföld - City Centre development axis as a potential focus of activity.

Increased travel activity resulting from economic growth

In addition to the forecast growth in population and employment based on urban planning and development assessments, the growth in the economy, its relation to car ownership, overall increase in trip rates and possible increase in public transport trips were also considered. The composite growth rate used for forecasting future Public Transport growth therefore takes into account both planning and economic growth assumptions.

In order to assist us determine the economic component of the overall growth rates we have undertaken a review of research studies into the relationship between the growth in public transport trips and economic growth, in this case growth in GDP; and the relationship between growth in public transport trips and car ownership. Our observations of the research from work in different countries is that the ranges of elasticity concluded from these studies are wide and indeed at times conflicting. It is not clear whether the differences are due to the stages of economic growth in the specific countries or other local issues. Our conclusion from this review was that there was no definitive relationship which could be applied to Budapest with confidence.

We therefore approached the issue based on our knowledge of overall growth/decline in public transport patronage in major cities together with the expressed policies of the Budapest municipality to maintain and further improve the existing modal share in favour of public transport within the context of increasing car ownership.

Our analysis of the historic trend in public transport patronage in Budapest showed that following a period of decline, patronage has stabilised since 1992/93 and has been relatively constant over the past two years. This is shown in Figures 9.3 and 9.4. Based on our knowledge and experience of other major cities and discussions with the study's steering committee we have made the assumption, for assessment purposes, that the component of the public transport patronage growth, which is attributable to the increase in travel activity resulting from economic growth, will result in trip levels remaining stable at study's base year (1994) level. Hence, the growth in patronage is directly related to the growth in population and employment levels.

Figure 9.3. Historic trend in public transport passenger trips in Budapest

Figure 9.4. Historic trend in public transport passenger kilometres in Budapest


Summary of overall growth rates

Table 9.3 hereafter shows the resulting overall travel demand growth rates based on the above assumptions together with the forecast trip ends for Budapest, at District level.

Passenger growth cut off

For the purposes of this study, it is assumed that patronage growth beyond 2020 is negligible and therefore the growth in passenger demand is assumed to cease at 2020. The economic growth however is assumed to continue, the effects of which will be reflected in the economic benefits of the scheme throughout the assessment period. This is explained in more detail in Chapter 10.

Conversion of all day to peak hour demand

For system design and operating analysis passenger flow data, and in particular link loadings, need to be expressed in peak hour flows per direction. As the modelling work is based on all day demand matrices, peak hour flows are not the standard output of the model and the model output needed to be converted to peak hour per direction. Our analysis of the relationship between peak direction flows to all day two-way flows established a general factor for converting two-way daily passenger flows to peak passenger flows per direction in the corridor.

Based on observed work peak and daily flows, we adopted conversion factors of 6% for bus and tram modes and 7% for LRT and metro modes to convert all day two way flows to peak hour peak direction passenger flows.


Table 9.3. Summary of Overall Growth Rates and trip ends by Districts

Districts
Growth Rates

1994 to 2020
Trip ends

1994
Trip ends

2020
I
0.995
73 06272 698
II
0.946
154 404145 997
III
0.952
161 298153 502
IV
1.099
122 150134 242
V
1.001
206 488206 705
VI
0.978
181 180177 136
VII
0.977
162 493158 777
VIII
0.967
196 807190 384
IX
0.092
172 880174 422
X
0.870
165 818144 191
XI
1.167
303 969354 593
XII
0.941
118 734111 692
XIII
0.844
250 271 211 140
XIV
0.855
246 913211 104
XV
1.127
92 016103 672
XVI
0.940
63 70759 885
XVII
0.946
61 65258 304
XVIII
0.920
82 12275 565
XIX
0.960
105 717101 535
XX
0.951
112 131106 661
XXI
1.006
100 166 100 750
XXII
1.019
49 724 50 657
SW Agglom.
1.817
40 238 73 104
Elsewhere
1.000
169 660 169 660
Totals
0.986
3 393 600 3 346 377



Transport networks

The transport demand matrix is assigned to the Do Minimum network and each alternative network and comparison of alternatives is made against the Do Minimum scenario as the benchmark case. The networks were developed as follows:

Do Minimum network

For the purposes of this study, the Do Minimum case is defined as the existing network plus the committed public transport improvements which are planned during the assessment period. Although a number of plans for improvements to the city's public transport system are available, there is no authoritative programme which can be considered as a reliable programme of improvements or one which have been endorsed by a city or national constitutional authority.

In the light of the above our assumptions with regard to the Do Minimum scenario was based on the following three main categories:

  1. Real committed improvements
  2. Essential upgrading/rehabilitation required to maintain the existing services in the corridor albeit at a lower level of service
  3. General public transport vehicle speeds

These are described below:

  • Real committed improvements

The only committed improvement in the corridor which could be realistically considered and included in the modelling process was the World Bank funded programme of tram track rehabilitation. It was not possible to obtain details of exact improvements to be undertaken over the whole city beyond the end of 1996. We understand that no fixed plan exists and that plans for improvements are drawn up on an annual basis for the following year. However plans for 1996 by fortunate coincidence concentrate on the south west corridor and these improvements are certain to be implemented particularly as the work on the majority of these planned improvements had already started in July 1996. These were the only improvements which were added as real committed improvements to the base network to produce the basis of the working assumptions with regard to the Do Minimum scenario.

These improvements include complete rehabilitation of the tram track over a 3 km length of Fehérvári út from Bocskai út/Október 23 út southbound (which is used by tram routes 18, 41 and 47) and rehabilitation of tram tracks on Irinyi József, Petöfi bridge, Ferenc krt and József krt to Blaha Square (which is used by tram routes 4 and 6). These improvements are assumed to improve tram speeds by 10% on the rehabilitated sections.

  • Essential up grading/rehabilitation required to maintain existing services in the corridor

Following discussions with the municipality, BKV and local experts, it has become clear that Szabadság bridge has significant structural weaknesses and it is unlikely that the bridge will be able to accommodate the two tram routes 47 and 49 for any significant length of time. It is envisaged that strengthening of the bridge will be implemented by 2005 if there was no prospect of the new system becoming operational by that year. Without this rehabilitation, Szabadság bridge could not continue to provide a route for the existing trams and diverting all passengers who currently use the tram services on Szabadság bridge to other adjacent river crossings is not considered a realistic long term solution.

  • General public transport vehicle speeds

Following discussions with the study's Steering Committee, it has been assumed that as highway congestion in Budapest increases, in the Do Minimum case, public transport vehicle speeds will decline by up to 20% over the next 25 years. This proportion is comparable with other major cities in particular with public transport vehicle speeds in London, where a similar reduction was observed between the early 1970's and early 1990's.

Alternative networks

Modelled networks were set up compatible with outline engineering plans for alternatives being assessed. Assumptions with regard to the alternatives tested are listed below:

  • Improvement of existing surface modes

For this alternative, it is assumed that there will be 'Super-Tram' type segregation of tram routes 47 and 49 from other highway vehicles which results in full segregation from the majority of other highway vehicles but not pedestrians. It is also assumed that on routes 47 and 49, new rolling stock will replace existing stock to improve speed, capacity and the general image of the tram services. Tram stops will remain in the same locations but will be reconstructed to allow more than one tram trainset boarding and alighting at one time.

For buses, it is assumed that bus lanes (painted lanes and with physical kerbs where existing highway geometry permits) will be introduced coupled with junction signal priority.

Overall it is assumed that the combined effect of the above public transport prioritisation segregation and new tram rolling stock will be a reversing of the effect of congestion on the public transport vehicle speeds plus a further improvement of speeds by 5% - i.e. a total improvement of surface public transport speeds in the corridor of 25% compared with the speeds in the Do Minimum scenario in 2020.

  • LRT and Metro options

Specification of these options and stations are as described in Chapter 5 of this report. They are assumed to be fully segregated, fully signalised with average commercial speeds of 28 kph.

For network development of LRT and Metro options, particular attention was paid to connections with the major existing services in the corridor. Where existing services could physically be connected to the new modes (to act as major feeders) these were incorporated in the model to ensure good network connectivity and interchange facilities onto the new modes.

The rationalisation of tram services were based on physical possibilities. For the LRT options running over Szabadság bridge, tram routes 18 and 19, which serve only Buda, were replaced with a bus service, providing a similar level of service. The tram services would not be able to continue as they would have had to share the track space with the new modes along Bartók Béla út on the approach to Szabadság bridge.

Tram route 49 was terminated completely and route 47 was terminated at Móricz Zsigmond Körtér as they were in direct competition with the new mode and served the same catchment area. It was not necessary to undertake a detailed reorganisation exercise for all the services in the corridor as this would be rather academic at this stage. Furthermore there is no benefit in undertaking such an exercise as the assessment of the operating cost savings for existing bus and tram services are based on passenger kilometres which assumes optimum rationalisation based on utilisation and demand for public transport services. Assessment of operating cost savings is explained in detail in Chapter 10.

Generated demand

As public transport travel conditions (reflected in the generalised cost of travel for each O-D pair) vary in the different alternatives and for different catchment areas it would be expected that the number of public transport trips would change accordingly. This effect has been modelled using an "elasticised matrix" methodology applying a generalised cost elasticity of -1.0 to each O-D pair. Thus, for example if an alternative reduces the generalised cost (relative to the Do Minimum) for a given O-D movement by 10% the model will show an increase in the public transport trips for that movement of +10% and vice-versa.

The generalised cost elasticity value of -1.0 is based on considerable international evidence of how public transport patronage is affected by changes in the attractiveness (measured by generalised cost values) of the system. This value encompasses the full range of responses that affect public transport trip making, e.g. diversion from car (as driver or passenger) diversion from walk or cycle and pure generation or induced trips. Table 9.4 shows a summary of estimated generated trips per day in 2020 for each alternative. Obviously those alternatives which have the largest effect upon the generalised cost has the greatest amount of generated trips.

Table 9.4. Estimated generated trips per day in 2020

Alternative
Generated trips
Improvement of existing surface modes 1.3
9 571
LRT via Bartók 2.2.1a
23 411
LRT via Fehérvári 2.2.2a
32 493
Metro via Bartók 3.3.1
40 213
Metro via Fehérvári 3.3.2
43 854
Metro via Tétényi 3.3.3
39 564



Our assumptions with regard to the proportion of the generated passengers which transfer from private vehicle mode to public transport is 30% of total trips generated. This proportion assumes good interchange and Park and Ride facilities and reflects the expressed policies of Budapest Municipality with regard to restraint measures in general.

Furthermore, it was assumed that the switch from private to public mode will result in corresponding relief on the highway network in the corridor which in addition to providing benefits to private car users will also result in an increase in public transport vehicle speeds. Our analysis has shown that the effect of the above on passenger forecasts for the new mode and sub-modal split is negligible. However, these effects have been incorporated in the study so that the benefits from them could be included in the economic assessments.

Private vehicle trips growth forecasts

We estimated the growth in private vehicle trips in Budapest and in particular for the area approximately within the second ring road in Pest and its natural continuation in Buda (i.e. Bocskai út, Október 23 út, Irinyi József út, Petöfi bridge, Ferenc Krt, József Krt., Erzsébet krt., Terez krt, Szt. Istvan krt, Margit krt, Krisztina krt, Alkotas út and Budaörsi út). Our underlying assumption with regard to the growth in private vehicle trips in Budapest is that it is a function of car ownership growth. A number of methods were tested for forecasting car ownership including:

  1. Time-series extrapolation:

1. based on District level data and

2. based on aggregated data for the whole of Budapest

  1. Cross sectional regression analysis by District.
  2. Econometric method developed by Quarmby and Bates.

Our analysis led us to work with the results of the econometric method which were considered as the most realistic of the methods tested. This results in an average car ownership growth of 1.5% per annum for the whole of Budapest. In the central area as outlined above, the growth in private vehicle trips is assumed to be around 50% of the aggregate car ownership growth for the whole of Budapest which represents an average composite growth rate of 0.75% per year.

Figure 9.5 summarises the adopted car ownership forecasts.

Figure 9.5. Historic growth and adopted forecasts car ownership for Budapest



Overall passenger forecasts

Tables 9.7 and 9.9 (refer to the end of the paragraph 9.8), present a summary of the 2020 two-way daily forecast passenger flows on the key sections of the network.

All LRT and metro alternatives provide significant relief to the existing public transport services within the corridor in particular on Erzsébet bridge where the relief is estimated as between 55% to 63% (4,000 to 5,000 passengers) during the peak hours in the peak direction mainly relieving the family 7 bus routes which compete with the LRT and metro services for trips of similar origin and destination. On Petöfi bridge relief of between 2,000 to 2,800 passengers (28% to 41%) is expected as a result of competition with tram routes 4 and 6.

The maximum loads of the LRT and metro services are expected to occur at the Danube crossing where they are expected to carry some 22,000 passengers during the peak hour in the peak direction or between 300,000 and 320,000 passengers in both directions per day. The current (1994) maximum load on the busiest existing metro line (line 3) is some 14,000 in the peak hour peak direction and 195,000 both directions per day.

Table 9.5 summarises the total passengers (boardings) on a new LRT or metro system, they are expected to range between around 420,000 (LRT via Bartók Béla) to some 515,000 (metro via Fehérvári) per day.

Table 9.5. Summary of daily passenger forecasts

Alternatives
Total daily passengers
LRT via Bartók 2.2.1.a
417 082
LRT via Fehérvári 2.2.2.a
463 800
Metro via Bartók 3.3.1
491 707
Metro via Fehérvári 3.3.2
514 702
Metro via Tétényi 3.3.3
496 370

Catchment area analysis

Finally, a pair-wise comparative analysis of the areas and population and employment served by each metro alignment was undertaken as a part of the short list assessment (LRT alignments being considered are identical to two of the metro alignments). This analysis is summarised in Table 9.8 and. It is evident that all alternatives serve identical catchment areas up to and including Móricz Zsigmond Körtér, beyond which (south and Southwest bound) the alignments take different routes.

Table 9.6. Year 2020 Population and Jobs served


Metro alternatives *
Population

served (P)
Jobs

served (E)
(P) + (E)

served
Metro via Bartók 3.3.1
51 450
33 670
85 120
Metro via Fehérvári 3.3.2
59 560
36 460
96 020
Metro via Tétényi 3.3.3
59 160
35 750
94 910

* All data is for the part of alignment within Buda only.

Table 9.7. Year 2020 forecast passenger flows on key sections of the network (All day two-way passenger flows)

Passenger flows
Total
Cross River
Passengers
Alternatives
Erzsébet
Szabadság
Petöfi
Bus 7s
Tram 47
Tram 49
Trams 4&6
New mode
Cross River
Do Minimum 131 421 112 680 113 055 98 909 56 218 56 462 102 669
-
820 188
Surface Option
Improv. of existing surface modes 1.3 123 810 108 884 132 942 92 577 53 057 55 818 124 969
-
823 749
Change from Do Minimum -7 611 -3 796 19 887 -6 332 -3 161 -644 22 300
-
3 561
%-6% -3%18% -6%-6% -1%22%
-
0.4%
LRT Options
LRT via Bartók Béla to Astoria 2.2.1.a 58 254 - 81 530 31 504 - - 73 718 307 553 905 954
Change from Do Minimum -73 167 -112 680 -31 525 -67 405 -56 218 -56 462 -28 951 307 553 85 766
%-56% -100% -28%-68% -100% -100%-28% 100% 10.5%
LRT via Fehérvári to Astoria 2.2.2.a 59 668 - 71 693 32 326 - - 63 685 318 945 911 509
Change from Do Minimum -71 753 -112 680 -41 362 -66 583 -56 218 -56 462 -38 984 318 945 91 321
%-55% -100% -37%-67% -100% -100%-38% 100% 11.1%
Metro Options
Metro via Bartók Béla to Keleti 3.3.1. 49 305 - 72 335 23 041 - - 65 356 310 979 858 892
Change from Do Minimum -82 116 -112 680 -40 720 -75 868 -56 218 -56 462 -37 313 310 979 38 704
%-62% -100% -36%-77% -100% -100%-36% 100% 4.7%
Metro via Fehérvári to Keleti 3.3.2. 50 257 - 66 958 23 513 - - 58 779 315 793 861 573
Change from Do Minimum -81 164 -112 680 -46 097 -75 396 -56 218 -56 462 -43 890 315 793 41 385
%-62% -100% -41%-76% -100% -100%-43% 100% 5.0%
Metro via Tétényi to Keleti 3.3.3. 48 255 - 71 494 21 689 - - 63 955 310 406 857 048
Change from Do Minimum -83 166 -112 680 -41 561 -77 220 -56 218 -56 462 -38 714 310 406 36 860
%-63% -100% -37%-78% -100% -100%-38% 100% 4.5%

Table 9.8. Year 2020 forecast passenger flows on key sections of the network (Peak Hour Peak Direction passenger flows)

Passenger flows
Total
Cross River
Passengers
Alternatives
Erzsébet
Szabadság
Petöfi
Bus 7s
Tram 47
Tram 49
Trams 4&6
New mode
Cross River
Do Minimum 7 885 6 761 6 783 5 935 3 373 3 388 6 160 - 49 211
Surface Option
Improv. of existing surface modes 1.3 7 429 6 533 7 977 5 555 3 183 3 349 7 498 - 49 425
Change from Do Minimum -457 -228 1 193 -380 -190 -39 1 338 - 214
%-6% -3%18% -6%-6% -1%22% 100% 0.4%
LRT Options
LRT via Bartók Béla to Astoria 2.2.1.a 3 495 - 4 892 1 890 - - 4 423 21 529 58 887
Change from Do Minimum -4 390 -6 761 -1 892 -4 044 -3 373 -3 388 -1 737 21 529 9 676
%-56% -100% -28%-68% -100% -100%-28% 100% 20%
LRT via Fehérvári to Astoria 2.2.2.a 3 580 - 4 302 1 940 - - 3 821 22 326 59 248
Change from Do Minimum -4 305 -6 761 -2 482 -3 995 -3 373 -3 388 -2 339 22 326 10 037
%-55% -100% -37%-67% -100% -100%-38% 100% 20%
Metro Options
Metro via Bartók Béla to Keleti 3.3.1. 2 958 - 4 340 1 382 - - 3 921 21 769 55 828
Change from Do Minimum -4 927 -6 761 -2 443 -4 552 -3 373 -3 388 -2 239 21 769 6 617
%-62% -100% -36%-77% -100% -100%-36% 100% 13%
Metro via Fehérvári to Keleti 3.3.2. 3 015 - 4 017 1 411 - - 3 527 22 106 56 002
Change from Do Minimum -4 870 -6 761 -2 766 -4 524 -3 373 -3 388 -2 633 22 106 6 791
%-62% -100% -41%-76% -100% -100%-43% 100% 14%
Metro via Tétényi to Keleti 3.3.3. 2 895 - 4 290 1 301 - - 3 837 21 728 55 708
Change from Do Minimum -4 990 -6 761 -2 494 -4 633 -3 373 -3 388 -2 323 21 728 6 497
%-63% -100% -37%-78% -100% -100%-38% 100% 13%