|
||||||||||||||||||||||||||||||||
BUDAPEST METRO LINE 4 FEASIBILITY STUDY Oktober 1996 |
Track |
|||||||||||||||||||||||||||||||
Introduction This chapter defines the main principles proposed for the design of
the tracks of Budapest Metro line 4. It includes the following paragraphs:
The main characteristics of the operating system are:
The design criteria considered are those described Chapter C-2. Definition of the different types of track laying Tracks are mainly located in tunnel and very partly in open air and
laid on a track bed delivered by the Civil Works. In tunnel, the track is recommended to be of a ballastless an antivibrating type. In open air, the track bed can be, according to the choices of the Civil Works, a road bed or a concrete invert, at grade level, on which the tracks shall be laid on ballast, refer to the below Figures C-12 & 13. Antivibrating ballastless track in tunnel The specified track is a track without rigid connection with the invert
(no elements imbedded in the concrete of the invert) and using concrete
sleepers, useless elements of the railway track. Called "STEDEF track", it has been used by the Paris metro
network since 1975 for all its new tracks in tunnel (about 60 km of
single track in operation) after tests of different types of ballastless
tracks (direct fastening on concrete with 1 or 2 elastic stages, Cologne
Eggs, etc.). It is also world wide used by many other underground networks
(of which recently Cairo City and Seoul) and railway tunnels, with a
total of about 400 km of single track. Compared to a conventional ballasted track, the vibratory speed reduction of the STEDEF track is about 10 dB; in some special cases it can increased to 14 dB by adding a second micro-cellular rubber pad.
The STEDEF ballastless track includes two elastic stages separated
by an heavy inertia support. The first stage, designed for medium frequency vibration damping,
consists of an elastic pad placed under the rail. The rail is fixed
by elastic clips fastened to the support. The heavy inertia support
consists of usual concrete sleepers, preferably twin-block (2 concrete
blocks linked by a steel bar). The second elastic stage, designed for law frequency vibration damping,
consists of a micro-cellular rubber pad placed beneath the block or
the head of the sleeper. An elastic boot wraps the pad and the lower
part of each sleeper block (or head) and is kept by an filling concrete
up to 10 cm above the lower part of the sleeper. The track is set up
in its final position by means of adjustable wedges giving a perfect
stability and allowing to obtain the required geometrical precision. The embedding concrete, put in place after the track adjustment, does not include any steel reinforcement or connection steel pin , except for possible steel bar or wire mesh for drainage of stray current. Outside ballasted tracks The ballasted track will be laid either on a subgrade of a road type
or on a concrete invert whose profile, slope of embankment, ditches
and materials will be defined by the Civil Works. The track will be equipped with concrete sleepers (excepted in some
short sections between points and crossings if they are equipped with
wooden sleepers) and elastic fastenings allowing rail welding in CWR
on main tracks. Sleepers will be inserted in a ballast layer whose theoretical profile
principle is defined by the below Figure C-10. The ballast normal thickness
between the upper part of the subgrade and the lower part of the sleepers
will be:
At the location between an underground ballastless track and an open-air
ballasted track on a subgrade, the ballasted track will continue over
30 metres inside the tunnel. Between a track laid in tunnel on a concrete invert and a track laid outside on subgrade with ballast, an inclined slab located under the ballast will ensure the rigidity transition.
Points and crossingsIntroduction Points and crossings are made up of turnouts which are used alone
or in crossovers, simple or double (scissors crossings). Three types of turnouts are defined:
As there are no international standards defining an unified range of points and crossings, the following characteristics could be replaced by those of similar equipment possibly used in Hungary. In this case, these characteristics shall be as similar as possible: same tangent, speed on the diverted track at least equal to the specified values, same technology. General characteristics The points and crossings shall be laid without cant. The layout of
the diverted track shall be designed in order to limit the cant deficiency
to 100 mm and the variation of cant deficiency to 90 mm/s. The design
shall also allow their setting up in Continuous Welded Rails (CWR). The foreseen general characteristics are given in the following Table
C-9:
* Except for the test track turnouts which should be of the tg 1/8 type. Operation, locking and control of the points tongues All the points shall be operated by electrical motors whose specification
shall be carried out by the Signalling. All the points and crossings crossed through by passengers trains
facing the point, or by any train at a speed 40 km/hr, shall be equipped
with individual, and untrailable, devices locking each tongue on its
stockrail. The operation of the locking device shall be performed by
the moving of the tongue, and the device shall also wedge each tongue
in its open position. Each tongue position shall be controlled by a device with electrical contacts allowing to make sure that each tongue is well in contact with its stockrail. Conductor rail Trains are supplied in 750 volts DC by a third rail. Vehicle collector
shoes will come into contact with the lower part of the rail. The conductor rail shall be a steel, law carbon rail fixed on the
track by monobloc insulators and shall be provided with a protective
cover fastened on the rail itself in order to give a maximum protection
against accidental contact. The rolling stock underframe gauge shall be specially designed in order to take into account that the ends approaches of the third rail are going upwards |